Summer months are the busy season for Knik Construction and, this year, crews wrapped up two projects in Bethel, AK. The Chief Eddie Hoffman Highway and the Bethel Parallel Runway Airport projects.
The Knik team worked hard repairing Chief Eddie Hoffman Highway at the request of the Alaska Department of Transportation. Roads take a beating in Alaska with freeze and thaw cycles creating potholes and crumbled asphalt erosion. Improvements to the Bethel highway included work on corners, shoulders and the installation of six inches of foamed asphalt with another four inches of asphalt on top. Knik has also installed culverts and added topsoil and hydro-seeding.
"Our work to improve roads and airports is very important to the Alaska economy and the health and safety of Alaska residents. These projects keep communities connected and maintain and protect the routes necessary to deliver essential goods," says Knik President Dan Hall. "We are entrusted with vital infrastructure projects and our employees take this responsibility seriously. We make every effort to hire as many local people as possible and finish our projects on time and within budget." Pictured above, Knik Flagger Wilson Green directed drivers to the work site in Bethel. Wilson is a local Bethel resident hired to work on the Chief Eddie Hoffman Highway project.
Knik also continued a long-term project to install a parallel runway and three taxiways at the Bethel Airport (pictured right). The project was split into three phases. Crews were most recently working on Phase III which called for expanding the primary runway safety area to a width of 500 feet along its entire 8,400-foot length.
A secondary runway embankment was constructed with a 4,600-foot by 150-foot runway safety area. Crews developed two material sites on airport property to supply the work. Over 1,000,000 cubic yards of sandy-silt material was excavated and hauled from these two sources. In prior phases, Knik installed a new standby generator module, electrical service, new runway lighting and underground fuel storage tank de-commissioning among other improvements.
As a general heavy construction company, Knik specializes in complex, logistically challenging projects in hard-to-reach places like remote bush Alaska, Guantanamo Bay, Wake Island and Midway Island. Knik crews work seasonally depending on the work which may mean moving materials via waterways in summer and constructing ice roads in the winter.
In addition to construction projects, each year Knik processes over 100,000 tons of gravel, rock, sand and other aggregate at its Platinum Pit and Quarry in Bethel. Gravel is shipped to remote sites in Western Alaska and other parts of the world by sister companies Bering Marine and Alaska Marine Lines.